Trident Tower-A
📍 Hyderabad · 90 Flats · Floor 1–9
TILE LAYING SCHEDULE
FLOOR 1 TILE PROGRESS
1 / 10 flats tiled
COMPLETION
–%
Loading…
QUICK ACCESS
Flat Tracker
90 flats · 103 items each
📅
Oct Schedule
Sep 28 – Nov 1
🛡️
Gate & Security
Visitors · Delivery · SOS
💬
Site Assistant
Ask anything about the site
OVERALL COMPLETION
–
of 90 flats
–
DONE
–
ACTIVE
–
PENDING
📅
32
WORK DAYS
👷
74
WORKERS/DAY
🏢
9
FLOORS
HANDOVER TARGETS
1
Floor 1
Target handover
1 Nov
31 days left
2
Floor 2
Target handover
1 Nov
31 days left
3
Floor 3
Target handover
1 Nov
31 days left
Flat Tracker
All 90 flats
–
–
–
complete
OCT WORK SCHEDULE
Tower-A · 3 Floors
1 Oct – 1 Nov 2026
32
WORK DAYS
64
PEAK WORKERS
10
ACTIVITIES
ACTIVITIES & WORKFORCE
#
ACTIVITY
TEAM
1
Chipping of loose material
All flats
6 machines
2
Waterproofing 1st coat + testing
Per floor · cure 2 days
8 members
3
Material shifting / dust removal
Daily · all floors
5 members
4
Plumbing – pipe check, laying & slope test
After WP 1st coat cure
8 members
5
Waterproofing 2nd coat + brick batting
After plumbing tested
10 members
6
Bathroom tile laying
After WP 2nd coat
10 members
7
Floor tiles + balcony + grouting
~1 week after bath tiles
10 members
8
Painting – common areas + flat interiors
Runs parallel all weeks
10 members
9
Common area light fixtures
Per floor
3 members
10
Common duct primer painting
All floors
4 julais
TOTAL PEAK WORKERS ON SITE
64
WEEK-WISE FLOOR PLAN
WEEK 1
1 Oct – 7 Oct
rest: Sun 5 Oct
1
Chipping → Floor 1
✓
WP 1st coat → Floor 1
3
Material shift → All floors
4
Plumbing → Floor 1 (after cure ~Oct 3)
8
Painting → Common areas
9
Common lights → Floor 1
10
Duct primer → Floor 1 & 2
WEEK 2
8 Oct – 14 Oct
rest: Sun 12 Oct
1
Chipping → Floor 2
✓
WP 1st coat → Floor 2
3
Material shift → All floors
4
Plumbing → Floor 2
5
WP 2nd coat → Floor 1
8
Painting → Common + Floor 1
9
Common lights → Floor 1 & 2
10
Duct primer → Floor 2 & 3
WEEK 3
15 Oct – 21 Oct
rest: Sun 19 Oct
1
Chipping → Floor 3
✓
WP 1st coat → Floor 3
3
Material shift → All floors
4
Plumbing → Floor 3
5
WP 2nd coat → Floor 2
6
Bath tiles → Floor 1
8
Painting → Floor 1 & 2
9
Common lights → Floor 2 & 3
10
Duct primer → Floor 3
WEEK 4
22 Oct – 28 Oct
rest: Sun 26 Oct
3
Material shift → All floors
5
WP 2nd coat → Floor 3
6
Bath tiles → Floor 2
7
Floor tiles → Floor 1
8
Painting → Floor 2 & 3
WEEK 5 · FINAL
29 Oct – 1 Nov
3 working days
3
Material shift → Final clearance
5
WP 2nd coat → Complete
6
Bath tiles → Floor 3
7
Floor tiles → Floor 2 & 3
8
Painting → Final touches Floor 3
🏆
ALL FLOORS HANDED OVER · 1 NOV 2026
SEQUENCE RULES
Chipping + WP 1st coat start together — Oct 1, Floor 1
Plumbing starts after WP 1st coat cure (~2 days per floor)
WP 2nd coat only after plumbing complete & tested
Bathroom tiling only after WP 2nd coat complete
Floor tiling follows bath tiling ~1 week per floor
Material shifting runs every working day throughout
Rest days: Oct 5, 12, 19, 26
Common Areas
Tower-A · Floors 1 – 9
Floor 1 — Common Areas
Gate & Security
Trident Tower-A
Log Visitor Entry
Fill details and allow or deny
TODAY'S VISITORS
Log Delivery
Parcel, food or courier at gate
DELIVERIES TODAY
Emergency SOS
Tap to alert guard + manager instantly
EMERGENCY CONTACTS
🚓
Police
100
🔥
Fire Brigade
101
🚑
Ambulance
108
📞
Disaster Helpline
1077
👷
Site Manager
–
🛡️
Security Gate
–
INCIDENT LOG
Vehicle Parking
Register and log vehicle movement
REGISTERED VEHICLES
VEHICLE MOVEMENT TODAY
My Gate Access
Pre-approve visitors for your flat
PRE-APPROVE VISITOR
MY PRE-APPROVALS
MY VISITOR HISTORY
MY DELIVERIES
Admin Dashboard
Full tower overview
SITE SETTINGS
ALL VISITORS
🏗️
Trident Assistant
Online · All 90 flats · AI-powered
Listening…
🔊 AUTO-SPEAK REPLIES
🏗️
🙏 Namaste! I'm your Trident Tower-A Intelligence Assistant.

I know all 90 flats, every work item, owner contacts, schedule, costs, contractor bills, common areas & gate logs.

Tap a chip below or ask me anything! Tap ✨ to connect Gemini AI for even smarter answers.
Alert Sent!
Guard & manager have been notified.
Stay calm. Help is on the way.